Project Description

Client:  Waukesha County
Location: 1500 N. University Drive, Waukesha, WI

Replacement of two Cleaver Brooks 16,737 MBH, firetube steam boilers and a Fulton condensing hot water boiler with new boilers to improve system efficiency, improve reliability, and reduce maintenance costs across the campus.

The campus heating plant is centrally located at the Field House facility.  Low pressure steam is distributed through tunnels to five separate locations on campus, each equipped with steam to hot water converters.

The project included updating the existing steam condensate pumps, steam to hot water convertors, deaerator/feed water equipment, boiler venting and piping in each of the mechanical rooms. New equipment controls were tied into the existing Waukesha County direct digital control system.